Genehmigung zur Änderung einer Anlage zur Erzeugung von Strom aus erneuerbaren Energien (Repowering) beantragen

Sachsen-Anhalt 99063001006003, 99063001006003 Typ 2

Inhalt

Leistungsschlüssel

99063001006003, 99063001006003

Leistungsbezeichnung

Apply for a permit to modify an installation for the generation of electricity from renewable energy sources (repowering).

Leistungsbezeichnung II

Apply for a permit to modify an installation for the generation of electricity from renewable energy sources (repowering).

Leistungstypisierung

Typ 2

Begriffe im Kontext

nicht vorhanden

Leistungstyp

Leistungsobjekt mit Verrichtung und Detail

Leistungsgruppierung

Immissionsschutz (063)

Verrichtungskennung

Genehmigung (006)

Verrichtungsdetail

within the scope of repowering of a plant for the generation of electricity from renewable energies

SDG Informationsbereiche

  • Erlangung von Lizenzen, Genehmigungen oder Zulassungen im Hinblick auf die Gründung und Führung eines Unternehmens

Lagen Portalverbund

  • Produkt- und Stoffzulassung (2120200)
  • Anlagenbetrieb und -prüfung (2120100)

Einheitlicher Ansprechpartner

Nein

Fachlich freigegeben am

03.03.2023

Fachlich freigegeben durch

Saxon State Ministry for Energy, Climate Protection, Environment and Agriculture (SMEKUL)

Teaser

If you intend to make changes to an installation that requires a permit and generates electricity from renewable energy sources, you must apply for a permit from the relevant authority.

Volltext

Do you operate a plant subject to immission control approval for which you already have immission control approval and plan to carry out repowering measures at this plant?

Repowering measures serve to modernize a plant for the purpose of generating electricity from renewable energies.

This repowering measure may cause adverse effects in relation to the current condition of the plant. Insofar as these are significant for the approval requirements of the plant requiring approval, a modification permit is required.

For this reason, corresponding modifications to plants requiring approval must be reviewed by the immission control authority. For this purpose, you must submit an application for a modification permit and provide all the documents required for the assessment. The application can be made in writing or electronically.

Erforderliche Unterlagen

  • Required drawings, plans, expert opinions
  • explanations and
  • Other documents (if necessary, ask the competent authority).

Voraussetzungen

The modification permit is issued if:

  • it is ensured that the obligations resulting from the requirements of the Federal Immission Control Act and the Federal Immission Control Ordinance are fulfilled, and
  • other regulations under public law and occupational health and safety concerns do not conflict with the construction and operation of the plant.

A permit for wind turbines within the scope of repowering may also not be refused if, after the modernization, not all immission guide values of the technical instructions for protection against noise are complied with, but

  • the immission contribution of the wind turbine after modernization is lower than the immission contribution of the wind turbines it replaces, and
  • the wind turbine corresponds to the state of the art.

Kosten

nicht vorhanden

Verfahrensablauf

You submit an application for a modification permit for the repowering measure to the responsible authority. You can submit the application electronically or in writing.

You enclose the documents required to assess the facts with the application.

After receipt of the application and the complete documents, the competent authority will check whether the modifications meet the requirements of immission control law. After final assessment by the competent authority, you will receive the decision in the form of an official notice.

Bearbeitungsdauer

3 Stunde(n)
The processing time starts from the receipt of the application and the complete documents.

Frist

Before making the changes

Weiterführende Informationen

nicht vorhanden

Hinweise

nicht vorhanden

Rechtsbehelf

  • Objection
  • Complaint

Kurztext

  • Modification of a plant requiring a permit according to BImSchG Permit in the context of repowering a plant generating electricity from renewable energies
  • If you want to modernize a plant requiring a permit that generates electricity from renewable energies, you need a permit for this project if and to the extent that
    • these modifications cause adverse effects in relation to the current condition of the plant and
    • these can be significant for the licensing requirements of the plant requiring a permit.
  • Application: EliA or in writing

Ansprechpunkt

State Administration Office

Zuständige Stelle

nicht vorhanden