Zustimmung zur Verlegung oder Änderung von Telekommunikationslinien beantragen

Saarland 99012104134000, 99012104134000 Typ 3

Inhalt

Leistungsschlüssel

99012104134000, 99012104134000

Leistungsbezeichnung

Requesting approval for the relocation or modification of telecommunications lines

Leistungsbezeichnung II

Requesting approval for the relocation or modification of telecommunications lines

Leistungstypisierung

Typ 3

Begriffe im Kontext

nicht vorhanden

Leistungstyp

Leistungsobjekt mit Verrichtung

Leistungsgruppierung

Baurecht (012)

Verrichtungskennung

Zustimmung (134)

SDG Informationsbereiche

nicht vorhanden

Lagen Portalverbund

  • Erschließung und Infrastruktur (2050300)

Einheitlicher Ansprechpartner

Nein

Fachlich freigegeben am

19.12.2024

Fachlich freigegeben durch

State Road Construction Agency (LfS) 30.03.2023 JZ

Teaser

As the owner or operator of a telecommunications line, you require the consent of the landowner to lay or modify this infrastructure. If the property is a public highway, you must submit the application to the responsible highway authority.

The link to the application portal is available to telecommunications companies and their service providers.

Volltext

If you are the owner or operator of a telecommunications line or a telecommunications network serving public purposes, you require the consent of the landowner to relocate or modify this infrastructure. If the property is a public traffic route, you must submit the application to the road owner. With the approval of the road owner, you can obtain any other necessary permits.

Once you have obtained all the necessary permits, you can generally start the construction work. Please note any conditions, ancillary provisions and agreed deadlines.

The "Broadband Portal" online service is available in more and more places. Its use offers the following advantages:

  • Clear presentation of your submitted applications and resubmission function
  • Provision of standardized formulations for statements and conditions
  • Direct communication option with the responsible authority
  • Interface option for integration into your own system environment, specialist procedures and GIS systems
  • Early coordination of restrictions or principles (installation guidelines) that the competent authority wishes to be observed during implementation
  • Early communication between the responsible authority and the telecommunications company (TKU) regarding the most effective route planning possible
  • All notifications and documents can be processed in digital form, thus ensuring seamless processing. This shortens response times, which means that the focus is on actual and widespread implementation.

For you as a company in the telecommunications industry, the digitized application process means a considerable simplification. The telecommunications company or service provider submitting the application is guided by the standardized application form so that relevant aspects can be transmitted easily. All notifications and documents are processed in digital form, thus ensuring seamless processing. The functional addresses set up ensure that applications are routed in a targeted manner or assigned to the relevant departments. This shortens response times and you will receive an answer to your request in a short time. This should also speed up the approval process.

Erforderliche Unterlagen

  • Map or geodata with exact location of the measure
  • Precise description of the measure (e.g. the components to be installed, information on quantities, masses and installation depth, time of implementation)
  • Right of way from the Federal Network Agency (BNetzA)
  • For service providers: additional power of attorney

- Right of way of the BNetzA

- Additional power of attorney for service providers

Voraussetzungen

  • You are the owner or operator of public telecommunications networks.
  • You are the owner or operator of public telecommunications lines.
  • You have been assigned the right of way by the Federal Network Agency.

You are the owner or operator of public telecommunications networks.

You are the owner or operator of public telecommunications lines.

You have been assigned the right of way by the BNetzA

Kosten

Fees are incurred, which the authorized user must transfer to the account specified in the corresponding notice of approval.

Verfahrensablauf

You can apply for line relocations in public traffic routes in writing or online.
The process begins with the application submitted by you as a telecommunications company and ends with the notice of approval from the road owner and its legally effective delivery.

  • When submitting the application, the construction project must be clearly described. This includes, for example, the exact location, the planned time period, the type of installation, material and installation depth.
  • Proof of the existing right of way must be submitted and, in the case of service providers, additional authorization from the telecommunications company.
  • The infrastructure manager checks the application documents and approves them.
  • The infrastructure manager has the option of attaching ancillary conditions to the approval, which you must take into account when implementing the measure.
  • The approval will be sent to you within 3 months of the application being submitted.
  • This period may be extended by one month if the application is more difficult. You will be informed of this.
  • If you have not received a notice of approval after three months, your application is deemed to have been approved.

You can apply for line relocations in writing or online. The process begins with the application and ends with the notice of approval from the infrastructure manager and its digital provision. You can also submit a preliminary request first.

  • As a telecommunications company or service provider, you submit your "Application for cable laying" via our website under the "Service" section and submit further documents here if necessary.
  • The application is submitted via the specified functional addresses.
  • Information on the implementation of the construction measure and the location/location must be entered.
  • You must show the route of the pipeline on informative plans and attach them to your application in digital form.
  • You can also enclose other documents relating to the construction project in digital form or in free form in your e-mail.
  • The infrastructure manager will process the application.
  • The approval notice will be sent to the telecommunications company or service provider by e-mail.

Bearbeitungsdauer

3 Monat(e)
If you have not received a notice of approval after three months, your application is deemed to have been approved. If the application is particularly difficult, the processing time may be extended by one month. You will be informed of this. In this case, the fictitious approval will only take effect after four months.

If the application is particularly difficult, the processing time may be extended by one month. You will be informed of this.

Frist

Genehmigungsfiktion: 3 Monat(e)
If you have not received a notice of approval after three months, your application is deemed to have been approved. If the application is particularly difficult, the processing time may be extended by one month. You will be informed of this. In this case, the fictitious approval will only take effect after four months.

There is no deadline for applicants.

Hinweise

If application documents are subsequently submitted or amended, the deadlines for processing by the infrastructure manager and, in particular, the deadlines for fictitious approval begin to run anew.

The application procedure can also be used for other applications for the laying of pipelines and/or applications for shared use.

Rechtsbehelf

An objection to the decision may be lodged within one month of notification.
The objection can be submitted in writing, in writing or electronically with a qualified electronic signature.

An objection may be lodged against the decision within one month of notification. The objection may be lodged in writing, by minute or electronically by e-mail with a qualified electronic signature.

Kurztext

  • Approval for cable laying in accordance with § 127 Telecommunications Act (TKG)
  • Application for telecommunications companies
  • for changes and relocations of telecommunications lines in traffic routes
  • The property concerned is a public thoroughfare
  • In writing or online
  • Approval by municipality, independent city, state or federal government
  • Prerequisite for companies:
    • Right of way from the Federal Network Agency (BNetzA)
    • For service providers, additional authorization from the telecommunications company

- OZG service Broadband expansion

- Approval for cable laying in accordance with § 127 Para. 1, 2, 3, 6, 7, 8 TKG

- Application for telecommunications companies or service providers

- for changes and relocation of telecommunications lines in traffic routes

- Approval by municipality or state

- Prerequisite for companies:

- Internet access for digital processing;

- Right of way from the BNetzA

- For service providers, additional authorization from the telecommunications company

Ansprechpunkt

nicht vorhanden

Zuständige Stelle

In principle, responsibility is divided along the road hierarchy:

  • Federal highways and federal roads: Autobahn GmbH
  • State roads I. and II. State roads of the first and second order: Landesbetrieb für Straßenbau (LfS), with exceptions
  • Municipal roads: the respective city or municipality

Further details are regulated by §56 of the Saarland Road Act

Formulare

  • Forms / online services available: Partially
  • Written form required: Yes
  • Informal application possible: Partially
  • Personal appearance necessary: No

Saarland - Application for cable laying