Unterlagen zur Genehmigungsfreistellung für die Änderung einer Anlage einreichen
Inhalt
Begriffe im Kontext
- Kauf und Verkauf von Immobilien, einschließlich aller Bedingungen und Pflichten im Zusammenhang mit der Besteuerung, dem Eigentum oder der Nutzung von Immobilien (auch als Zweitwohnsitz)
- Hausbau und Immobilienerwerb (1050100)
- Bauplanung (2050400)
- Bauverfahren (2050500)
Fachlich freigegeben am
Fachlich freigegeben durch
For a submission under the exemption from approval, you must also submit the required building documents in accordance with the State Building Regulations (LBO) in conjunction with the Building Documents Ordinance (BauVorlVO).
You have the right to choose and therefore also the option of having your building project checked in the simplified building permit procedure in accordance with § 64 LBO.
Please note that all requirements in accordance with Section 63 (1) and (2) LBO must be met, otherwise the exemption from approval cannot be granted.
For a submission under the exemption from approval, you must also submit the required building documents in accordance with the State Building Regulations (LBO) in conjunction with the Building Documents Ordinance (BauVorlVO).
You have the right to choose and therefore also the option of having your building project checked in the simplified building permit procedure in accordance with § 64 LBO.
Please note that all requirements in accordance with Section 63 (1) and (2) LBO must be met, otherwise the exemption from approval cannot be granted.
Mandatory documents:
- Parcel map, § 2 BauVorlVO
- Proof of building use § 6 BauVorlVO
- Description of the building plot, § 5 BauVorlVO
- Description of the building structure, § 5 BauVorlVO
- Site plan, § 3 BauVorlVO
- Construction drawings, § 4 BauVorlVO
- Calculations of building figures, § 5 BauVorlVO
Depending on the type of building project and the location of the building plot, further building documents can or must be submitted. These are, for example
- Description of the combustion plant (§5 BauVorlVO)
- Description of operations for commercial construction projects
- In addition to the content of the description of operations in accordance with Section 5 BauVorlVO, further information on the type of planned use may be required, in particular to assess the permissibility under building planning law.
- Structural engineering certificates in accordance with § 67 LBO e.g:
- Stability § 8 BauVorlVO
- Fire protection § 9 BauVorlVO
- Thermal insulation, sound insulation, vibration protection § 9 BauVorlVO
- Presentation of the site drainage § 7 BauVorlVO
Survey form in accordance with the Building Construction Statistics Act for the survey of construction measures at the time of approval or consent or at the time at which they may be carried out on the basis of state procedural regulations
Mandatory documents:
- Parcel map, § 2 BauVorlVO
- Proof of building use § 6 BauVorlVO
- Description of the building plot, § 5 BauVorlVO
- Description of the building structure, § 5 BauVorlVO
- Site plan, § 3 BauVorlVO
- Construction drawings, § 4 BauVorlVO
- Calculations of building figures, § 5 BauVorlVO
Depending on the type of building project and the location of the building plot, further building documents can or must be submitted. These are, for example
- Description of the combustion plant (§5 BauVorlVO)
- Description of operations for commercial construction projects
- In addition to the content of the description of operations in accordance with Section 5 BauVorlVO, further information on the type of planned use may be required, in particular to assess the permissibility under building planning law.
- Structural engineering certificates in accordance with § 67 LBO e.g:
- Stability § 8 BauVorlVO
- Fire protection § 9 BauVorlVO
- Thermal insulation, sound insulation, vibration protection § 9 BauVorlVO
- Presentation of the site drainage § 7 BauVorlVO
Survey form in accordance with the Building Construction Statistics Act for the survey of construction measures at the time of approval or consent or at the time at which they may be carried out on the basis of state procedural regulations
The municipality has one month to notify whether planning permission is required or whether it will apply for a provisional prohibition.
The municipality has one month to notify whether planning permission is required or whether it will apply for a provisional prohibition.
You have the right to choose and therefore also the option of having your building project examined in the simplified building permit procedure in accordance with Section 64 LBO.
It is possible to apply for an exemption from approval for special building structures. In this case, no building permit is required from the responsible lower building supervisory authority.
It is possible to apply for an exemption from approval for special building structures. In this case, no building permit is required from the responsible lower building supervisory authority.