Immissionsschutz - Betriebseinstellung einer genehmigungsbedürftigen Anlage nach BImSchG anzeigen
Inhalt
Begriffe im Kontext
Fachlich freigegeben am
Fachlich freigegeben durch
Bundes-Immissionsschutzgesetz (BImSchG):
- § 15 Änderung genehmigungsbedürftiger Anlagen
Decommissioning of installations requiring authorisation must be reported to the competent authority in accordance with Section 15 (3) of the Federal Immission Control Act (BImSchG) as soon as the operator has decided to do so.
The notification must be accompanied by documents on the planned measures to fulfil the aftercare obligations arising from Section 5 (3) and (4) BImSchG.
If you intend to cease operating an installation that requires authorisation under immission control legislation, you must notify the authority responsible for the installation immediately, stating the date of cessation in accordance with Section 15 (3) of the Federal Immission Control Act (BImSchG) Authority responsible for the installation.
When decommissioning a plant that requires authorisation under immission control legislation, you must fulfil the aftercare obligations arising from Section 5 (3) and (4) BImSchG:
- No harmful effects on the environment and other hazards, significant disadvantages and significant nuisances for the general public and the neighbourhood may be caused by the plant or the plant site after decommissioning.
- Waste must be properly and harmlessly utilised or disposed of without impairing the welfare of the general public.
- The site must be restored to a proper condition.
You must immediately notify the authority responsible for your installation of the intended decommissioning of an installation requiring authorisation under immission control legislation, together with the necessary documents. The competent authority will check whether the operator obligations have been fulfilled. If further documents are required for an assessment, these must be submitted subsequently.
You must report the decommissioning of installations requiring authorisation as soon as you as the operator have made a decision to do so.
If the authority responsible for your installation offers an online application for the notification of a change to an installation requiring authorisation under immission control law in accordance with Section 15 (1) BImSchG, you can also use this for the notification of a cessation of operations in accordance with Section 15 (3) BimSchG.
Coordinate in advance with the responsible immission control authority regarding the documents required for an assessment.
Please make sure that you submit the notification to the immission control authority responsible for your plant requiring authorisation under immission control law.