Anlage zur Erzeugung von Strom aus erneuerbaren Energien (Repowering): Genehmigung für die Änderung beantragen

Mecklenburg-Vorpommern 99063001006003, 99063001006003 Typ 2a

Inhalt

Leistungsschlüssel

99063001006003, 99063001006003

Leistungsbezeichnung

Plant for the generation of electricity from renewable energies (repowering): Apply for approval for the change

Leistungsbezeichnung II

Applying for approval to modify an installation for the generation of electricity from renewable energies (repowering)

Leistungstypisierung

Typ 2a

Begriffe im Kontext

nicht vorhanden

Leistungstyp

Leistungsobjekt mit Verrichtung und Detail

Leistungsgruppierung

Immissionsschutz (063)

Verrichtungskennung

Genehmigung (006)

Verrichtungsdetail

as part of the repowering of a plant for the generation of electricity from renewable energies

SDG Informationsbereiche

  • Erlangung von Lizenzen, Genehmigungen oder Zulassungen im Hinblick auf die Gründung und Führung eines Unternehmens

Lagen Portalverbund

nicht vorhanden

Einheitlicher Ansprechpartner

Nein

Fachlich freigegeben am

nicht vorhanden

Fachlich freigegeben durch

Federal Ministry for the Environment, Nature Conservation, Nuclear Safety and Consumer Protection (BMUV) Ministry for Climate Protection, Agriculture, Rural Areas and the Environment Mecklenburg-Western Pomerania 15.07.2024

Teaser

If you intend to make changes to a system that requires approval and generates electricity from renewable energies, you must apply for approval from the responsible authority.

Volltext

Do you operate an installation that requires approval under immission control legislation, for which you already have approval under immission control legislation, and are you planning to carry out repowering measures on this installation?

Repowering measures serve to modernize an installation for the purpose of generating electricity from renewable energies.

This repowering measure may have adverse effects in relation to the current state of the installation. If these are significant for the approval requirements of the installation requiring approval, a modification permit is required.

Therefore, corresponding changes to installations requiring approval must be reviewed by the immission control authority. To do this, you must submit an application for a modification permit and submit all the documents required for the assessment. The application can be made in writing or electronically.

Erforderliche Unterlagen

  • application
  • Required drawings, plans, documents
  • Explanations of the installation/project
  • Other documents (if necessary, ask the competent authority (ELiA checklist))

Voraussetzungen

You must prove that you will fulfill the obligations of the Federal Immission Control Act when modifying the system.

Kosten

Fees are charged for the official act. The amount is primarily based on the installation costs of the facility or the administrative costs. Further details are regulated by the Immission Control Costs Ordinance M-V.

Verfahrensablauf

If you wish to apply to the competent authority for a change to an installation requiring approval (repowering), you must first submit the application documents in full.

You can do this in writing or electronically. The competent authority will confirm receipt of the application in writing or electronically, check it for completeness and, if necessary, involve other specialist authorities.

If necessary, the authority will request further documents.

Bearbeitungsdauer

6 months for the formal procedure
3 months for the simplified procedure

Frist

There is no deadline.

Weiterführende Informationen

nicht vorhanden

Hinweise

nicht vorhanden

Rechtsbehelf

  • Objection
  • Complaint

Kurztext

  • Modification of a plant requiring approval according to BImSchG
  • Approval of an installation as part of repowering to generate electricity from renewable energies
  • If you want to modernize a plant that requires approval and generates electricity from renewable energy sources, you need approval for this project if and to the extent that
    • these changes will have a negative impact in relation to the current state of the installation and
    • these may be significant for the approval requirements of the installations requiring approval.
  • Application: electronic application under immission control law (EliA) or in writing
  • Responsible: immission control authority

Ansprechpunkt

nicht vorhanden

Zuständige Stelle

State Offices for Agriculture and the Environment (StÄLU), Department 5

Formulare

nicht vorhanden