Vereinfachtes Verfahren nach BImSchG Genehmigung

Hamburg 99063014006000 Typ 2

Inhalt

Leistungsschlüssel

99063014006000

Leistungsbezeichnung

<div lang="en-x-mtfrom-de">Simplified procedure according to BImSchG approval</div>

Leistungsbezeichnung II

<div lang="en-x-mtfrom-de">Apply for a permit using the simplified procedure for a plant under the Federal Immission Control Act</div>

Leistungstypisierung

Typ 2

Begriffe im Kontext

<div lang="en-x-mtfrom-de">Federal Immission Control Act, permits</div> (Synonym), <div lang="en-x-mtfrom-de">Federal Immission Control Act</div> (Synonym)

Leistungstyp

nicht vorhanden

SDG Informationsbereiche

nicht vorhanden

Lagen Portalverbund

nicht vorhanden

Einheitlicher Ansprechpartner

Nein

Fachlich freigegeben am

18.12.2023

Fachlich freigegeben durch

nicht vorhanden

Handlungsgrundlage

§ 19 Law on the protection against harmful environmental effects caused by air pollution, noise, vibrations and similar processes (Federal Immission Control Act BImSchG)
https://www.gesetze-im-internet.de/bimschg/__19.html

Fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Installations Requiring Approval - 4th BImSchV) Appendix 1
https://www.gesetze-im-internet.de/bimschv_4_2013/anhang_1.html

Teaser

Are you applying for approval of installations using the simplified procedure?
You can then obtain a permit from the competent authority to construct and operate facilities of a certain type or size without public participation.

Volltext

You can obtain approvals for systems of a certain type or scope using a simplified procedure. In this case, the procedure takes place without public participation.

Erforderliche Unterlagen

  • written or electronic application
  • required drawings, plans or reports
  • Explanations of the system
  • If necessary, the responsible authority will provide you with further documents

Voraussetzungen

  • You apply for the simplified procedure within an application for approval and construction or substantial modification.
  • You must prove that you will fulfil the obligations of the Federal Immission Control Act when constructing and operating a plant.
  • The project does not conflict with any other public law regulations or occupational health and safety concerns.

Kosten

Fees apply. The amount of the fees depends on the investment amount or the administrative costs. They are calculated based on the Hamburg Environmental Fees Ordinance.

Verfahrensablauf

You submit a written or electronic application.
The responsible authority will check your application and your documents for completeness.
If necessary, they may request further documents or information from you.
The simplified procedure takes place without public participation. No documents or plans are made available. There is no hearing.
Once the responsible authority has determined all the circumstances that are relevant for granting a permit, it will decide on the application. You will receive a written decision with the reasons for the decision.

Bearbeitungsdauer

The processing time is 3 months after receipt of all necessary documents.

Frist

You need the permit before you can start constructing or operating the facilities.

Hinweise

No

Rechtsbehelf

  • Contradiction
  • Action before the administrative court

Kurztext

  • Apply for a permit using the simplified procedure for a plant under the Federal Immission Control Act
  • Apply for authorisation for installations of a certain type or size using a simplified procedure
  • Granting of approval using a simplified procedure, i.e. without public participation

Ansprechpunkt

nicht vorhanden

Zuständige Stelle

Authority for the Environment, Climate, Energy and Agriculture

Formulare