Änderung einer genehmigungsbedürftigen Anlage nach BImSchG Entgegennahme

Hamburg 99063001261000 Typ 2

Inhalt

Leistungsschlüssel

99063001261000

Leistungsbezeichnung

<div lang="en-x-mtfrom-de">Modification of a facility requiring approval under the Federal Immission Control Act (BImSchG)</div>

Leistungsbezeichnung II

<div lang="en-x-mtfrom-de">Report a change to a facility requiring approval</div>

Leistungstypisierung

Typ 2

Begriffe im Kontext

<div lang="en-x-mtfrom-de">harmful environmental impact systems</div> (Synonym), <div lang="en-x-mtfrom-de">Federal Immission Control Act</div> (Synonym), <div lang="en-x-mtfrom-de">Federal Immission Control Act</div> (Synonym)

Leistungstyp

nicht vorhanden

SDG Informationsbereiche

nicht vorhanden

Lagen Portalverbund

nicht vorhanden

Einheitlicher Ansprechpartner

Nein

Fachlich freigegeben am

08.12.2023

Fachlich freigegeben durch

nicht vorhanden

Handlungsgrundlage

§ 15 Federal Immission Control Act (BImSchG)
https://www.gesetze-im-internet.de/bimschg/__15.html

Teaser

If you wish to make a change to a facility for which you have not yet applied for approval, you must notify the responsible authority.

Volltext

If you plan to make a change to the location, condition or operation of a facility that requires approval, you must notify the responsible authority. This also applies to changes that are relevant to a major accident or if you intend to cease operations.

Erforderliche Unterlagen

  • Notification form, for example from the ELiA online service
  • Required drawings, plans, reports
  • Explanations and
  • other documents that you receive from the competent authority.
You must attach to the notification all the documents that may be necessary to check whether the project requires approval.

Voraussetzungen

The planned changes to the facility appear to have only minor adverse effects and do not require approval.

If the competent authority considers that a permit is necessary, an authorisation procedure must be carried out in accordance with Section 10 of the Federal Immission Control Act.

Kosten

Fees apply. The amount of the fee depends on the investment amount or processing effort.

Verfahrensablauf

  • You notify the responsible authority of the planned change in writing or electronically via the online service.
  • They shall attach to the notification the necessary documents to the extent that these may be necessary for the examination as to whether the project requires approval.
  • The competent authority will confirm receipt of the notification and the
  • the documents attached without delay in writing or electronically; in the case of an electronic notification, it may request additional copies and the transmission of the documents to be attached to the notification also in written form.
  • After receiving your notification, the applicant will inform you immediately of any additional documents it requires to assess your requirements.
  • If necessary, the competent authority decides that your project requires a permit. The authority will inform you of its decision within one month.
  • You may implement the change as soon as the competent authority informs you that the change does not require approval or if the competent authority has not commented within one month after the notification documents have been completed.
  • If you make a change that is relevant to a major accident, you may only make the change once the responsible authority informs you that no approval is required.

Bearbeitungsdauer

The processing time is 1 month from the time the complete documents are received by the responsible authority.
In the case of changes relevant to incidents, the processing time is 2 months from the time the complete documentation is received by the responsible authority.

Frist

Notify the responsible authority of any planned changes to your facility requiring approval at least one month before they are implemented. Notify any changes that are relevant to a major accident at least two months before they are implemented.

Hinweise


Notification is only required if the change may affect the protected assets listed in Section 1 of the Federal Immission Control Act.

Rechtsbehelf

no

Kurztext

  • Report a change to a facility requiring approval
  • At least one month before the planned change to an installation
  • If no approval is required
  • Report in writing or online with ELIA online service

Ansprechpunkt

nicht vorhanden

Zuständige Stelle

Authority for the Environment, Climate, Energy and Agriculture

Formulare